Posted on Jul 29, 2017

It’s trite but true: time is money. And in the construction industry, this saying is particularly pertinent.If a project can’t be completed on time, it may result in penalties and other unwanted repercussions, not to mention the harm to a construction company’s reputation. And, in the worst case scenario, the firm may not get paid at all.

Terms of the Contract

Delays in construction aren’t unusual and are usually covered by the terms of the contract. Typically, contracts set a number of deadlines, with penalties for failing to complete each on time, barring any special circumstances. Of course, looming large is the ultimate deadline — the substantial completion date.

Besides a final payoff, the substantial completion date may affect other matters, including state and local government requirements, payments to third parties, availability of tax incentives and responsibilities to lenders. It can’t be viewed in a vacuum.

The specifics will vary, but the list of elements governed by contract terms likely is to include the following items.

Identification of deadlines.

In some cases, the contract will specify a hard-and-fast calendar due date, such as the end of business at 5 pm (insert time zone) on December 31, (insert year). Alternatively, you might tie the completion date to a specific event such as one year after the municipality issues a building permit or two years after the contract is signed.

If you use a date tied to an event, make sure that the language in the contract is clear. Also, check to avoid deadlines that occur on a weekend or holiday or make appropriate adjustments (for example, the next business day).

Excused delays.

This is often at the crux of conflict between construction firms and clients, so it’s important that excused delays are ironed out in the contract. An “excused” delay is one that couldn’t have been reasonably foreseen before the parties signed the contract.

When possible, be specific regarding events that would result in an excused delay. For example, a strike by vendors providing raw materials might be listed as an excused delay. Conversely, inclement weather might not be allowed as an excused delay, depending on the geographic location of the project.

Excused delays can be a significant negotiating point and your interests may lie in whether your firm is the general contractor or a subcontractor. Although it may be difficult to resolve these issues at the outset, it could save plenty of hassle — not to mention legal fees — by coming to a clear agreement in the contract.

Money.

If delays are caused by factors outside of your control, your firm may require an increase in pricing to meet the specs of the project. Again, your needs may vary based on your role in the process, and you might specify increases for certain types of excused delays and not for others.

Owner-caused delays.

Even though construction firms often cause delays, the fault may lie with the property owner. For instance, an owner might make substantial revisions to the building plans, fail to point out flaws in the design or other problems after work has already started or simply procrastinate when important decisions must be made. Similarly, a subcontractor may be held back by the actions, or inactions, of a general contractor.

As you might imagine, this can turn into a contentious issue, so again it’s best to address contingencies in the contract. It must be established whether the delay is caused by one party or multiple parties and how the penalties and extra costs should be allocated. It’s best to clearly define the terms before problems occur and rely on an exact formula for attributing costs.

Finally, note that delays may occur because the owner fails to make good on certain promises, such as payment at different stages of the project. It’s logical that the construction firm shouldn’t bear the burden of this type of delay and terms in the contract may address these situations.

Notification.

When a delay occurs — by either party to the contract — notification is generally required. Typically, this responsibility is triggered after a designated number of days, such as 30 days after a deadline is missed. Failure to provide proper notification will often result in a waiver of rights and price adjustments.

Not only does this provision ensure that delays are legitimate, it creates a timeline that can be easily verified, thereby ensuring enforcement of contract terms. However, frequent delay notifications may also be a nuisance and hurt the relationships of the parties. Consider this in your negotiations.

Overview of Damages

In a typical situation, one of the parties will suffer damages when delays push back completion of the project. For example:

  • Damages to property owners. Due to delays, property owners may end up losing rental income, future tenants, public incentives and tax benefits, and financing opportunities, just to name several of the main possibilities. It may also require additional interest costs on loans and other related expenditures.
  • Damages to construction firms. A firm will likely face additional overhead costs when a project drags on past the stated deadline. In addition, revenue will be lost when crews remain tied up on the job when they could be working elsewhere.

These consequential damages also may be reflected in the contract. However, based on the language of the contract, it may not be possible to recover such damages, especially when they’re speculative in nature. It may be difficult to prove the dollar value with a reasonable certainty, so some costs may have to be absorbed.

Finally, consider the aspect of liquidated damages. These are damages agreed upon in the contact if one party breaches the contract. For instance, liquidated damages may apply if a contractor breaches the contract by missing the substantial completion deadline.

This provision generally stipulates an amount (such as $1,000 for every day the project is late). The amount is usually deducted from the project price. It should be noted that liquidated damages are often contested as to the enforceability of the provision and the calculation of the damages.

Review Closely

Pay close attention when you enter into a deal no matter how profitable it initially appears. Have your legal advisor draw up the contract to help ensure you’re adequately protected in the event of any significant delays.

Airport Delays

Some construction delays have higher profiles than others.

Case in point: Work on the new $1 billion “people mover” and remote rental car facility at Tampa International Airport (TIA) is currently running more than four months behind schedule.

Problems are to be expected, of course, but some of these caught the parties by surprise, such as:

  • Travelers kept getting in the way of construction crews.
  • Workers discovered storm drains near the people mover station at the main terminal, so the foundation had to be redesigned.
  • A soil problem was discovered under the people mover route connecting the remote parking garage and rental car facility with the main terminal. Again, the foundation had to be redesigned.

Initially, the project was supposed to be completed by October 2017. Now TIA officials will gladly settle for an opening before spring break in 2018.